Lake County & Clermont Commercial Permits: Step by Step
How commercial building permits work in Lake County and Clermont, FL, from zoning and site plan approval to inspections and the certificate of occupancy.

A commercial building permit in Lake County or Clermont is the end of a sequence, not the start. Zoning and site approvals come first, then a complete submittal, then plan review, inspections and closeout. This guide walks through each step using the published requirements of Lake County and the City of Clermont. Requirements change, so confirm current checklists with the reviewing office before you submit.
Step 1: Confirm who has jurisdiction
Start by confirming whether the parcel is inside a city or in unincorporated Lake County.
- Inside Clermont city limits, the City handles site review and building permits through Clermont Building Services. The City’s site review process also applies to projects that use city utilities.
- In unincorporated Lake County, the Office of Planning & Zoning reviews land development, and Lake County Building Services issues the building permit.
For local context on growth and self-storage demand, see Clermont, FL growth and self storage demand.
Step 2: Zoning and site plan approval
The building permit depends on approved zoning and site plans.
In Lake County
The County’s New Commercial Structure Permit Checklist (CL35) lists an approved zoning permit and approved site plan as required items. The checklist also notes that these approvals remain valid for submitting the building permit application only for a limited period, so plan the building submittal soon after site approval.
In Clermont
The City’s Development Review Packet sets the order:
- A mandatory pre-application conference with a conceptual plan.
- A formal electronic site submittal with complete plans, including landscape, irrigation, elevations and geotechnical reports where applicable.
- Reviewer comments and resubmittals until every reviewer approves and the plans are stamped.
- A pre-construction meeting with the City’s Environmental Services staff, with the required bond in place.
Uses that are not permitted in the zoning district, or that do not meet city codes, need a Conditional Use Permit or Variance, according to the City’s site review page.
Zoning: where self storage is allowed
Self storage is permitted in some zoning districts and not others, so confirm the parcel’s zoning and the allowed uses with the City or County before design starts. Where a use needs extra review, the Conditional Use Permit or Variance path adds a step before site plan approval.
Step 3: Check the Green Swamp Area of Critical State Concern
Part of Lake County lies within the Green Swamp Area of Critical State Concern. Lake County’s Land Development Regulations, Chapter VIII define development broadly there, including construction, land clearing, excavation and placing fill. CL35 lists Green Swamp review as a separate item where it applies. Confirm the parcel’s status before design, since it can shape the site layout. Stormwater also deserves early attention: Clermont reviews drainage and floodplain compliance during plan review, and South Lake County’s lakes and terrain make grading a defining part of most site plans.
Step 4: Assemble the submittal
Lake County checklist items
Based on CL35, a new commercial structure submittal includes:
- A building permit application signed by the license holder or an authorized agent, with subcontractors listed by issuance.
- Construction plans signed and sealed by an architect or engineer, submitted digitally through the County’s online portal (or paper plans with original seals, in office).
- Energy calculations from a Florida-registered design professional, if applicable.
- Product approval numbers, if they are not on the plans.
- The approved zoning permit and site plan.
- Proof of a septic permit application, if applicable.
- Green Swamp review, if applicable.
The County’s plan submittal requirements (BF51) also set the format for electronic plans: a single landscape PDF with an index on the cover sheet and matching bookmarks.
Clermont plan requirements
Clermont’s Building Permit Packet asks for signed and sealed architectural and structural plans, a site plan, a soils report, structural calculations and local design loads, including wind loads. Electronic plans must be digitally signed and sealed, combined into one landscape PDF and allow reviewer mark-ups. Incomplete submittals are rejected and not reviewed until complete.
Step 5: Product approvals
Florida requires many exterior building products, such as windows, doors, roofing and wall panels, to carry a state or local product approval. The Florida Building Commission’s product approval search lists approved products. Selecting approved products during design keeps plan review from stalling on substitutions.
Step 6: Impact fees, conceptually
Impact fees are one-time charges on new development for public facilities. Clermont sets its fees in Land Development Code, Chapter 111, covering parks and recreation, police, fire, and water and wastewater. Lake County runs its own impact fee program and publishes its current fee schedules there, organized by land use. The County notes that some commercial and industrial projects may qualify for deferral or waiver. Fees depend on the land use category, so a mini-warehouse is classified differently from other uses, and both city and county fees can apply depending on location. Check the current schedules and confirm with staff at the pre-application meeting rather than relying on past figures.
Step 7: Plan review
In Clermont, Building Services first checks the application for completeness, then routes it to Plans Review. Reviewers check the Florida Building Code along with local zoning, drainage and floodplain rules, and the Fire Department, Public Works and Utilities may also review. After all reviews are complete and the plans are approved, the permit is issued.
Step 8: Record the Notice of Commencement
Under Florida Statutes section 713.13, the owner records a Notice of Commencement before starting the improvement and posts a copy at the site. Section 713.135 requires a copy to be filed with the permitting authority before the first inspection when the direct contract exceeds the statutory threshold; otherwise, later inspections cannot be performed or approved. Lake County’s CL35 adds that the property owner, or an authorized member of the owning entity, signs the notice. The statute also tells owners to consult their lender or an attorney before recording if financing is involved.
Step 9: Inspections
After the permit is issued, inspections are scheduled at each phase of construction. Clermont allows inspection requests online or by phone, according to Building Services. The approved plans must stay on the job site for inspectors. Clermont also requires stamped site plans at the job site, as noted on the site review page.
Step 10: Certificate of occupancy
When all required inspections are approved, Clermont’s Permitting Section finalizes the permit and issues a Certificate of Occupancy or a Certificate of Completion, as appropriate. The building can be occupied only after that certificate is issued.
How a design-build team keeps the sequence moving
A design-build team owns this whole path. It confirms jurisdiction and Green Swamp status, prepares for the pre-application meeting, coordinates site and building documents, chooses approved products, tracks the Notice of Commencement, and manages inspections through the certificate of occupancy. For an example in Clermont, see the self storage facility we designed and built on Hooks St.: self storage construction on Hooks St. in Clermont. Learn more on our self-storage sector page. The facility is owned and operated by Sunny Storage, an affiliated company.
FAQ
Do I go to the City or the County?
It depends on whether the parcel is inside Clermont city limits. Inside the city, start with Clermont’s site review process. In unincorporated areas, start with Lake County Planning & Zoning.
Is a pre-application meeting required in Clermont?
Yes. The City’s Development Review Packet lists a mandatory pre-application conference with a conceptual plan.
Where do I find current impact fees?
In Clermont’s Land Development Code, Chapter 111, and on Lake County’s impact fees page. Confirm with staff during pre-application.
Does the Green Swamp affect my site?
Only if the parcel is inside the designated area. Lake County lists Green Swamp review as a separate checklist item where it applies.
Planning a commercial project in Lake County? Contact i4 Capital Group to review your site and permit path.
Sources checked October 28, 2026.
Updated